Restrictions from week 45

21.10.2019

Information about possible restrictions for testing activities during renovation work at the proving ground of ATP from week 45

restrictions

High Speed Oval (ORK) 

Access and exit and lanes 4 and 5 are closed in the construction area from December 04 – 17, 2019. The construction area can, however, be passed around at a speed of max. 80 km/h.

Wet Handling Track (NHK)

Full closure from week 45 - 48.

Durability Road South (DLK–Süd)

Partial closure from week 45 - 50 from the access to the Vehicle Dynamics Area (FDY) up to the Banked Road (SFB).

Roundabouts 1 and 2

Closure of roundabout 2 from week 45 – 47. 

Closure of roundabout 1 from week 49 – 50. 

Rough Road (SWS)

Partial closure from week 45 - 46. Depending on which module is currently being renovated, the other modules are available.

Vehicle Dynamics Area (FDY)

Full closure sector 4 (tangent) from week 45 – 47

The other sections of the Vehicle Dynamics Area can be used without restrictions. Please coordinate your project with the FDY coordinator on site.


Of course, we will make every effort to minimise the impact for our customers on the proving ground. However, due to possible weather changes, time shifts may occur.

In case short-term changes should occur, we will inform you immediately. Please note the Customer Information System (KIS) and the daily driving instructions. 

Should you have any questions or require additional information, please contact our test and safety coordinator Holger Schäfer, phone: +49 4961 975 322. 

Thank you very much for your understanding!

Your ATP team