Friction coefficients Wet Handling Track

27.07.2020

Status update

After another evaluation, it became clear that we were able to achieve our goal of a homogeneous BPN value for the skid-pad, the front area from the presentation area to the skid-pad and the rear area from the skid pad to the entrance to roundabout 2 through our measures. The value is now 40 BPN in each of these areas.
Now the last area from the entrance to the presentation area has to be adjusted, which will be further coordinated with the test operation.